Plan • actual • forecast

Investor reporting for construction projects

I combine the estimate, construction schedule, workforce resources, project cash flow, KPIs and risks in one report. During supervision, the plan is compared with actual progress.

View example

Anonymised example

Apartment building roof replacement

The final report compares the approved budget and schedule baseline with actual performance, showing variances and the project outcome.

Project data

Client details and the exact project address are hidden in this public example.

828 m² · amounts excluding VAT
Approved budget baseline
136 790
EUR
Actual cost
138 330
EUR
Actual progress
100%
works completed
Actual duration
32
workdays
Average workforce
6
people

Budget control

From the initial offer to the fixed price

Changes are separated from the original baseline so the investor can see how and why the project budget changed.

Budget change structure

Share of the final fixed price

Initial offer
115 421,52
Additional scope
8 289,90
Price update
13 078,58
Approved budget baseline136 790,00 EUR
Actual cost: 138,330.00 EUR. Budget overrun: +1,540.00 EUR. The additional cost arose from unforeseen rebuilding of a small section of the eaves masonry.

Investor control questions

The rationale and decision for each change are recorded in the report.

01
What changed?

Additional works, quantities or prices.

02
Why did it change?

Technical, contractual or market rationale.

03
What is the impact?

Budget, time, resources and risks.

Construction schedule

25-workday delivery plan

The schedule covers five working weeks. Rain days are excluded, so calendar duration may increase.

Work section
N1
N2
N3
N4
N5
Setup and scaffolding
Lift on site
Demolition works
Batten installation
Membrane installation
Standing-seam installation
Shaft and eaves repairs
Handover and documentation
Main worksSupport / parallel worksPlant and handover

Project cash flow

Weekly costs, receipts and funding risk

Cash flow must be aligned with the schedule and payment terms. The baseline below comes from the estimate appendix.

IndicatorN1N2N3N4N5After completionTotal
Scheduled earned value26 458,7540 252,3240 496,9519 036,6910 545,290,00136 790,00
Material prepayments46 938,521 338,820,000,000,000,0048 277,34
Labour and plant21 807,7926 505,6124 700,649 493,246 005,380,0088 512,66
Total expenditure68 746,3127 844,4324 700,649 493,246 005,380,00136 790,00
Client receipts68 395,000,0041 037,0020 518,500,006 839,50136 790,00
Net cash flow in period−351,31−27 844,4316 336,3611 025,26−6 005,386 839,500,00
Cumulative cash flow at period end−351,31−28 195,74−11 859,38−834,12−6 839,500,00—
Payment model50% / 30% / 15% / 5%
Maximum forecast funding gap−28 195,74 EUR (N2)
Control actionConfirm interim payment dates and funding cover before contract.

KPI and plan-to-actual control

Project completed — baseline compared with actuals

The final indicators show actual cost, progress, duration and average workforce, together with variances against the approved baseline.

KPIBaselineActualVarianceStatus
Budget136 790,00 EUR138 330,00 EUR+1 540,00 EUROver budget
Actual progress100%100%0 percentage pointsCompleted
Duration25 workdays32 workdays+7 workdaysDelay
Workforce resource5–6 workersAverage 6 peopleIn line with planOn plan
Forecast completion5 working weeks6 weeks+1 weekLater than plan

Risk register and forecast

Issues the investor should see before a decision

The risk register records the basis, potential impact, required action and status. Below are initial issues identifiable from the baseline data.

Weather impact

Rain days are excluded from the schedule; calendar completion may change. The schedule forecast should be updated weekly.

MONITOR

Material prepayments and deliveries

A material prepayment is planned in week one. Orders, delivery dates and title conditions should be checked before payment.

BEFORE START

Cash-flow gap in week 2

The baseline shows cumulative cash flow of −28,195.74 EUR at the end of week 2. Interim payment timing or funding cover must be clarified before contract.

CLARIFY

Change control

Additional scope and the price update changed the initial offer. Further changes should be approved before execution.

ONGOING CONTROL

Regular investor report

What the investor receives

The reporting period is agreed in the contract — for example weekly, monthly or before a material decision.

01
Executive summary

Main changes, decisions and forecast on one page.

02
Budget and changes

Approved baseline, actual cost, commitments, variance and forecast final cost.

03
Schedule and resources

Plan versus actual, delays, critical works and workforce loading.

04
Cash flow

Planned and actual payments, funding need and forecast.

05
KPIs, risks and decision log

Owners, deadlines, open issues and recommended action.

Service price

Investor reporting within Premium+ construction supervision

Regular investor reports are prepared within the Premium+ construction supervision service. The price depends on project size, construction stage, reporting frequency and the required level of detail.

View Premium+ scope and current price

An investor needs a clear picture, not a pile of files

I prepare a project-control baseline and regular investor reports linking the estimate, schedule, resources, cash flow and supervision data.