Weather impact
Rain days are excluded from the schedule; calendar completion may change. The schedule forecast should be updated weekly.
MONITORPlan • actual • forecast
I combine the estimate, construction schedule, workforce resources, project cash flow, KPIs and risks in one report. During supervision, the plan is compared with actual progress.
Anonymised example
The final report compares the approved budget and schedule baseline with actual performance, showing variances and the project outcome.
Client details and the exact project address are hidden in this public example.
Budget control
Changes are separated from the original baseline so the investor can see how and why the project budget changed.
Share of the final fixed price
The rationale and decision for each change are recorded in the report.
Additional works, quantities or prices.
Technical, contractual or market rationale.
Budget, time, resources and risks.
Construction schedule
The schedule covers five working weeks. Rain days are excluded, so calendar duration may increase.
Project cash flow
Cash flow must be aligned with the schedule and payment terms. The baseline below comes from the estimate appendix.
| Indicator | N1 | N2 | N3 | N4 | N5 | After completion | Total |
|---|---|---|---|---|---|---|---|
| Scheduled earned value | 26 458,75 | 40 252,32 | 40 496,95 | 19 036,69 | 10 545,29 | 0,00 | 136 790,00 |
| Material prepayments | 46 938,52 | 1 338,82 | 0,00 | 0,00 | 0,00 | 0,00 | 48 277,34 |
| Labour and plant | 21 807,79 | 26 505,61 | 24 700,64 | 9 493,24 | 6 005,38 | 0,00 | 88 512,66 |
| Total expenditure | 68 746,31 | 27 844,43 | 24 700,64 | 9 493,24 | 6 005,38 | 0,00 | 136 790,00 |
| Client receipts | 68 395,00 | 0,00 | 41 037,00 | 20 518,50 | 0,00 | 6 839,50 | 136 790,00 |
| Net cash flow in period | −351,31 | −27 844,43 | 16 336,36 | 11 025,26 | −6 005,38 | 6 839,50 | 0,00 |
| Cumulative cash flow at period end | −351,31 | −28 195,74 | −11 859,38 | −834,12 | −6 839,50 | 0,00 | — |
KPI and plan-to-actual control
The final indicators show actual cost, progress, duration and average workforce, together with variances against the approved baseline.
| KPI | Baseline | Actual | Variance | Status |
|---|---|---|---|---|
| Budget | 136 790,00 EUR | 138 330,00 EUR | +1 540,00 EUR | Over budget |
| Actual progress | 100% | 100% | 0 percentage points | Completed |
| Duration | 25 workdays | 32 workdays | +7 workdays | Delay |
| Workforce resource | 5–6 workers | Average 6 people | In line with plan | On plan |
| Forecast completion | 5 working weeks | 6 weeks | +1 week | Later than plan |
Risk register and forecast
The risk register records the basis, potential impact, required action and status. Below are initial issues identifiable from the baseline data.
Rain days are excluded from the schedule; calendar completion may change. The schedule forecast should be updated weekly.
MONITORA material prepayment is planned in week one. Orders, delivery dates and title conditions should be checked before payment.
BEFORE STARTThe baseline shows cumulative cash flow of −28,195.74 EUR at the end of week 2. Interim payment timing or funding cover must be clarified before contract.
CLARIFYAdditional scope and the price update changed the initial offer. Further changes should be approved before execution.
ONGOING CONTROLRegular investor report
The reporting period is agreed in the contract — for example weekly, monthly or before a material decision.
Main changes, decisions and forecast on one page.
Approved baseline, actual cost, commitments, variance and forecast final cost.
Plan versus actual, delays, critical works and workforce loading.
Planned and actual payments, funding need and forecast.
Owners, deadlines, open issues and recommended action.
Service price
Regular investor reports are prepared within the Premium+ construction supervision service. The price depends on project size, construction stage, reporting frequency and the required level of detail.
View Premium+ scope and current priceI prepare a project-control baseline and regular investor reports linking the estimate, schedule, resources, cash flow and supervision data.